This hypothetical Myers Park project assumes an $850,000 property purchase followed by demolition and a 4,200 sq ft replacement home. Its line items total $2,554,000; they are modeling assumptions, not actual project evidence.
Project Overview
- Location: Myers Park, Charlotte
- Original Home: 1965 ranch, 2,200 sq ft (demolished)
- New Home: 4,200 sq ft, 5BR/4.5BA custom
- Total Project Cost: $2,554,000
- Hypothetical resale assumption: $2,350,000
- Modeled loss before sale costs: $204,000
Complete Cost Breakdown
| Category | Cost |
|---|---|
| Property Purchase (lot + teardown) | $850,000 |
| Demolition & Site Clearing | $28,000 |
| Architectural Design & Engineering | $72,000 |
| Permits & Impact Fees | $22,000 |
| Construction (4,200 sq ft) | $1,260,000 |
| Landscaping & Hardscape | $65,000 |
| Smart Home Systems | $35,000 |
| Pool (heated, with cover) | $85,000 |
| Construction Loan Interest (16 months) | $52,000 |
| Temporary Housing (14 months) | $42,000 |
| Moving & Storage | $8,000 |
| Change Orders | $35,000 |
| Total | $2,554,000 |
Why Tear Down?
The original 1960s ranch had:
- Outdated floor plan (closed-off rooms, small kitchen)
- Aging mechanical systems (HVAC, electrical, plumbing all original)
- Foundation settling issues requiring $40K+ in repairs
- Renovation estimate of $450K — only getting 2,200 sq ft
By tearing down and rebuilding, they got exactly what they wanted on an irreplaceable Myers Park lot.
Construction Details
| Spec | Detail |
|---|---|
| Foundation | Conditioned crawlspace |
| Framing | 2x6 walls, engineered trusses |
| Exterior | Fiber cement siding + stone accents |
| Windows | Marvin Ultimate (wood interior) |
| Kitchen | Custom inset cabinets, Wolf/Sub-Zero |
| Primary Bath | Heated marble floors, steam shower |
| HVAC | 3-zone variable speed, SEER 20 |
| Smart Home | Lutron lighting, Sonos whole-home, Control4 |
| Pool | 15x30 heated with automatic cover |
Timeline
- Months 1–3: Design and architecture
- Month 4: Demolition and site prep
- Month 5: Permits (six-week scenario assumption, not a jurisdiction commitment)
- Months 6–7: Foundation and framing
- Months 8–10: Mechanical, roofing, exterior
- Months 11–14: Interior finishes
- Months 15–16: Landscaping, pool, punch list
Financial Analysis
This scenario demonstrates why a teardown can lose money:
- Lot value: $850K (Myers Park lots are irreplaceable)
- Construction cost: $300/sq ft (premium but not ultra-luxury)
- Resulting home value: $2.35M ($560/sq ft — a hypothetical value, not a market observation)
- Modeled result: $304K loss before selling costs; this scenario does not support an investment-return claim
How to use this scenario
Replace every allowance with a written project-specific quote. Confirm what is excluded, whether fees overlap, and how unknown work is authorized. Do not interpret the schedule or resale assumption as a guarantee.